Wire cutting is very common in current production and processing. In the process of calculating the price, the processing area is usually used to quote. So I often see people asking: how much is a square meter of wire cutting processing. However, in wire cutting processing, there will be such a rule that if the thickness is less than 20mm, the processing cost will be calculated according to 20mm. If it is larger than 20mm, it is calculated according to the actual object.

Calculate the price of wire cutting from the working hours: the calculation of processing fee is 5 yuan per hour for ordinary fast wire cutting below 500mm, 8-10 yuan per hour for more than 500mm, 8 yuan per hour for slope less than 5 degrees, and 8 yuan per hour for more than 500mm 5 degrees for 12 yuan per hour. Medium wire is 15 yuan per hour.
Calculate the price of wire cutting from the area: the conventional production of fast wire cutting is 0.3 yuan per square meter, (note: if there is a large slope and complicated processing procedures, it will be calculated separately). Medium wire feeding is generally 1 yuan per square meter, (Note: If you encounter complex processing methods, you can increase the quotation appropriately).
Calculation of wire cutting processing fee
Wire cutting is divided into fast wire cutting and slow wire cutting. Ordinary wire cutting is generally calculated according to the wire cutting area, and the height of the workpiece is also high and the corresponding price will be high. The price of slow wire cutting is about 10 times that of ordinary wire cutting.
Slow wire processing in Jiangsu and Zhejiang areas generally costs 60 yuan per hour (the average cutting efficiency is 40-60mm/min), but the mold cutting with higher precision costs 80 yuan, because once it is scrapped, you need to pay for the material.
1. Single piece or small batch processing
Wire cutting processing fee = (cutting section area / 1200) * 5 Note: 1 hour wire cutting 1200 square millimeters, the general charge is 5 yuan.
2. Large quantities: the price can be slightly lower than this standard
Calculation of processing time: required time = processing cross-sectional area/(1200-1800), note: 1200-1800 is a parameter that can be adjusted, but most of the processing will choose the middle number of 1500, so that it is multiplied by processing per hour Fees can be obtained for mass processing prices.
For fast silk, some can be calculated at 0.01 yuan/mm, 0.005 yuan/mm, and 10 yuan/hour.
One cut for WEDM is 0.03 yuan/mm, two cuts for slow WEDM are 0.038 yuan/mm, three cuts for slow WEDM are 0.045 yuan/mm, and four cuts for slow WEDM are 0.055 yuan/mm.
In the process of wire cutting quotation, the price of wire cutting processing per square meter will also have certain differences due to different regions or materials. If the quotation is made according to the market price, there will be some errors more or less. Therefore, in order to make accurate quotations, operators need to perform multi-party calculations in fixed practice to obtain scientific and accurate quotations.

 

 